This is the main service of Naguilian Water District where anyone within the service area of NWD can apply for a Water Service. A Water Service Connection will be installed once the proper fees and materials will be paid.

Office or Division:Finance and Commercial Division
Classification:Complex
Type of Transaction:G2C – Government to Citizen G2B – Government to Business G2G – Government to Government
Who may Avail:All
CHECKLIST OF REQUIREMENTSWHERE TO SECURE
1 Water Service Application FormNWD Administrative Bldg., Naguilian, La Union
1 Photocopy of Proof of Ownership of the House and Lot (Tax Declaration, Land Title, or Notarized Deed of Absolute Sale)Registry of Deeds, Notary Public, Municipal Assessor’s Office, Office of the Provincial Assessor
1 Photocopy of Valid IDGSIS, SSS, LTO, CAAP, MARINA, PRC, BIR, OWWA, PSA, PhilHealth, Post Office, OSCA, Barangay, COMELEC, PAG-IBIG, PNP, Company, DFA
1 Original Affidavit of Undertaking if land is not under the name of the applicantPublic Attorney’s Office, Private Law Offices
Authorization Letter (if applicant will tap on the line of an active concessionaire)Active Concessionaire of where line will be tapped.
IF BEING REPRESENTED
Authorization LetterProperty Owner, Person/company being represented
STAGE 1: PRE – INSPECTION
CLIENTS STEPAGENCY ACTIONFEES TO BE PAIDPROCESSING TIMEPERSON RESPONSIBLE
1. Applicant will accomplish the New Water Connection Form from the Public Assistance and Complaint Desk.1. PACD Representative will validate the submitted documents and process the applicationnone5 minutesPublic Assistance and Complaint Desk Representative
2. Applicant will pay the inspection fee and will receive the Official Receipt2.1. Cashier will issue an Official Receipt   2.2. PACD Representative will validate the Official Receipt and will generate a Service Request to be forwarded to the next divisionInspection Fee: Php200.003 minutesFinance and Commercial Division         Public Assistance and Complaint Desk Representative
TOTAL:Php200.008 minutes 
STAGE 2: ON-SITE INSPECTION
CLIENTS STEPAGENCY ACTIONFEES TO BE PAIDPROCESSING TIMEPERSON RESPONSIBLE
1. Applicant is informed on the scheduled on-site inspection1.1. Advice the Applicant on the scheduled on-site inspectionnone5 minutesEngineering, Construction, Production and Water Quality Division
2. none2.Conduct on-site inspection and estimate the costnone1 hourEngineering, Construction, Production and Water Quality Division
3. acknowledges the inspection findings and estimated cost3. explains the findings and shows the detailed view of the cost of the new connection.none5 minutesEngineering, Construction, Production and Water Quality Division
TOTAL:none1 hour and 10 Minutes 
STAGE 3: PAYMENT OF FEES AND SIGNING OF CONTRACT
CLIENTS STEPAGENCY ACTIONFEES TO BE PAIDPROCESSING TIMEPERSON RESPONSIBLE
1. Applicant will be briefed with the rules and regulations and the policies of the Water District3.  Assigned Representative will brief the applicant on the policies and on the rules and regulation of the Water Districtnone15 minutesAdministrative and General Services Division
3. none4. General Manage reviews and approves the Contractnone5 minutesOffice of the General Manager
2. Applicant will pay the Application Fee and Water Connection Fees2.Cashier will accept the payment and will issue an Official ReceiptPhp 300.00 + Amount of Water Connection Fees quoted5 minutesFinance and Commercial Division
TOTAL:Php 300.00 + Amount of Water Connection Fees quoted30 Minutes 
STAGE 4: INSTALLATION AND CONNECTION
CLIENTS STEPAGENCY ACTIONFEES TO BE PAIDPROCESSING TIMEPERSON RESPONSIBLE
1. Applicant will be informed of the scheduled installation date1.Advice the applicant on the scheduled installation datenoneSeven (7) Days after processing the paymentPublic Assistance and Complaint Desk Representative
2. Applicant will acknowledge the Water Service Installation2.Engineering Division will install and tap the Applicant into the current Water SystemnoneDepends on the severity of the installationEngineering, Construction, Production and Water Quality Division
TOTAL:noneDepends on the severity of the installation 

* Installation Of Water Service Connection is qualified for Multi-Stage Processing

Table A: FEES AND MATERIALS

Fees related to New Connection
Application FeePhp 300.00
Inspection FeePhp 200.00
FITTINGS (Standard Connection)
1Pc Water MeterPhp 1,500.00
1 Pc Saddle Clamp 2 x ½” (P)Php 350.00
1 Pc Saddle Clamp 2 x ¾” (P)Php 350.00
1 Pc Saddle Clamp 2 x 1” (P)Php 350.00
1Pc Saddle Clamp 3 x ½” (P)Php 425.00
1Pc Saddle Clamp 3 x ¾” (P)Php 425.00
1Pc Saddle Clamp 3 x 1” (P)Php 425.00
1Pc Saddle Clamp 4 x ½” (P)Php 450.00
1Pc Saddle Clamp 4 x ¾” (P)Php 450.00
1Pc Saddle Clamp 4 x 1” (P)Php 450.00
1Pc Saddle Clamp 4 x 1” (GI)Php 600.00
1Pc Saddle Clamp 6 x ½” (P)Php 1,000.00
1Pc Angle ValvePhp 650.00
1Pc Plastic Elbow ½”Php 45.00
1Pc Plastic Nipple 12 x ½”Php 130.00
1 Pc Plastic Union Coupling ½”Php 200.00
1 Pc Plastic Union Coupling ¾”Php 250.00
1 Pc Plastic Union Coupling 1”Php 300.00
1 Pc Plastic Male Adaptor ½”Php 120.00
1 Pc Plastic Male Adaptor ¾”Php 160.00
1 Pc Plastic Male Adaptor 1”Php 200.00
1m HDPE Pipe ½”Php 35.00
1m HDPE Pipe ¾”Php 50.00
1m HDPE Pipe 1”Php 70.00
1Pc Meter SealPhp 75.00